SA: Western Aqueduct back on track

SOUTH AFRICA:

The entire 55 km second phase of the much needed Western Aqueduct begins at Inchanga Station and ends at Ntuzuma, and includes two branch pipelines to Tshelimnyama and Mount Moriah. It is expected to significantly strengthen the capacity of bulk water supply to the western regions of eThekwini, injecting up to 400 Mℓ/d. At the same time, it will ultimately boost much needed water supplies to the north of Durban.

The head of eThekwini Water and Sanitation (EWS), Neil Macleod, says EWS has unbundled the 55 km pipeline project into six individual projects that will be rolled out over a seven-year period. It was initially intended to be constructed as a single, large contract but has been dogged by delays.

The second sector, covering the stretch between Alverstone Neck and Ashley Drive in Kloof and worth a similar value, has been released for tendering purposes.

The eThekwini Municipality called for expressions of interest last year and 16 contractors were selected for two different panels – one comprising companies qualified to deal with large diameter pipes and  the other capable of working with pipes of a smaller diameter. Cycad Pipelines won this tender on a competitive bid against the other pre-qualified contractors in the large diameter pipe category. The rest of the contracts will be competitively tendered between the pre-qualified contractors making up the two panels.

“Further delays to this project will have detrimental consequences for Durban as current water supply infrastructure is unable to cope with the forecast future water demand. In addition to large commercial and industrial projects on the drawing board, the city’s population is expected to increase by at least 20% by 2030,” Macleod warns.

Commissioned in June 2011, the first phase of the Western Aqueduct covered 19 km from Umlaas Road to Inchanga Station. Lessons learnt from that project will further refine the environmental rehabilitation for the second phase, he states.

Source Article from http://www.infrastructurene.ws/2013/08/16/western-aqueduct-back-on-track-2/
Western Aqueduct back on track
http://www.infrastructurene.ws/2013/08/16/western-aqueduct-back-on-track-2/
http://www.infrastructurene.ws/feed/
Infrastructure news

Leave a Reply

Your email address will not be published. Required fields are marked *



Note that external content is often used in creating news articles on this site. If you want to use the content, please ensure that the relevant source is referenced, as indicated at the end of the article.
Also note that, although we source high-quality content, we cannot verify or be held accountable for the accuracy of external media content. News articles also do not necessarily reflect the views or opinion of the NEPAD Water Centres of Excellence Network